West Wing, Penticton Lakeside Resort and Conference Centre

Location

Penticton, B.C.

Size

4,665 square metres

Completion

2017

Architect

HDR, Inc.

Structural Engineer

RJC Engineers

Construction Manager

Greyback Construction

Wood Supplier

Mercer Mass Timber LLC

Wood Species

Douglas-fir

Project Materials

Cross-laminated timber (CLT)

Glue-laminated timber (Glulam)

Structural Systems

Mass timber

Mid rise

Post + beam

Prefabricated

Locally produced CLT for six-storey hotel

Speed of construction, reduced building weight, and the cachet of a timber design convinced the owners of Penticton Lakeside Resort to use wood instead of concrete when expanding their waterfront resort.

  • Six-storey structure completed in just under one year, a target impossible without using cross-laminated-timber (CLT).
  • Use of exposed glue-laminated timber (glulam) and CLT in both rooms and public spaces give the hotel a contemporary look, while also saving money by eliminating the need to add interior finishes.
  • Locally-produced CLT panels were used for all major shear elements of the building, including floor and roof structures, balcony separation walls, and the vertical walls which separate the exterior decks.

Why mass timber for hotel: speed, lightweight, and cachet of timber design

Situated on the south end of Okanagan Lake, an area popular with tourists and locals alike for its recreational activities, wineries, and fruit orchards; this six-storey, 70-unit hotel sets a new standard for the use of mass timber in commercial and hospitality projects.  

Lakeside Resort’s owner wanted to open the doors to the new hotel in time for the busy summer season. The six-storey structure was completed in just under one year, and all project members agree that meeting the target completion date would not have been possible without using cross-laminated timber (CLT) .

The property is located on a flood plain in Penticton, and most new buildings in the area need to be built on pilings, so the lightweight nature of wood was a definite advantage. By using CLT, the overall building weight was reduced, allowing them to use a more traditional concrete foundation instead of pile foundations, saving money and time.

The compromised soil conditions of the floodplain site meant that the reduced weight of mass timber compared to concrete lowered the construction costs significantly. Each floor consists of 70 locally produced CLT panels. 

A unique and modern addition to Penticton’s waterfront

The exposed timber structure—made of a Douglas-fir glue-laminated timber (glulam) post-and-beam frame with CLT floors, roof, shear walls, stairwells, and stairs—envelops visitors with a sense of warmth and modern rusticity. Glulam was also used to build a dramatic nine-metre-high wall using a double lattice of beams to frame the windows.  

The floor panels were loaded on the truck at the factory not far from the site and lifted by crane and lowered into place in a single movement. Each floor took an average of one week to install and the entire building was completed in just under a year, in time for the resort’s busy summer season.   

There’s a lot of money left on the table if you miss a summer at a resort like this. When you compress a construction schedule by using prefabricated wood panel products, it results in real, intended financial benefits.

David Prystay, General Manager, RPB Hotels & Resorts

Case study: West Wing, Penticton Lakeside Resort carbon balance analysis

Duncan Griffin from HDR Seattle explains the concept of triple net-zero buildings and the role of embodied carbon. The video features Penticton Lakeside Resort as an example to explain carbon balance analysis.